/Case Study:
Catalyst Housing Group
Creekwood Apartments
Download Case Study →

2 weeks

four fully leveled hard bids

9-month

improvement of pre-construction
timeline

Customer Overview

Catalyst Housing Group’s innovative model provides affordable rental housing to California's essential workforce. During the past two years, Catalyst has acquired more than $2 billion and 4,000 units of premier multifamily rental communities. Catalyst Housing Group lives at the intersection of investment, innovation and impact. The company was founded in 2015 and headquartered in Larkspur, CA.

Challenges

In April 2021, Catalyst Housing Group purchased the Creekwood Apartments from Bridge Investment Group and paid $128,750,000, or $416,666 per unit. Situated in the East Bay community of Hayward, CA, the 309-unit complex spans 257,000 square feet and features several pools, a gym and a clubhouse.

Previously, extensive site access was needed to measure and scope a renovation that included units, exteriors, amenities and common areas. Next, Catalyst would typically source an interior designer who would site-walk, re-design and specify FF&E for the clubhouse, gym, lobbies and hallways on four floors. A sizable portion of the 500+ man-hours needed pre-construction would require Construction Operations to compile design packages for RFPs, gather and finally level-set multiple contractor bids. Multiple new hires would be required to manage a renovation of this scale. If any takeoffs were discovered to be inaccurate mid-project, costly change orders, rework loops and rebidding would be required to move forward.

2 weeks

four fully leveled hard bids


9-month

improvement of pre-construction timeline

Customer Overview

Catalyst Housing Group’s innovative model provides affordable rental housing to California's essential workforce. During the past two years, Catalyst has acquired more than $2 billion and 4,000 units of premier multifamily rental communities. Catalyst Housing Group lives at the intersection of investment, innovation and impact. The company was founded in 2015 and headquartered in Larkspur, CA.

Challenges

In April 2021, Catalyst Housing Group purchased the Creekwood Apartments from Bridge Investment Group and paid $128,750,000, or $416,666 per unit. Situated in the East Bay community of Hayward, CA, the 309-unit complex spans 257,000 square feet and features several pools, a gym and a clubhouse.

Previously, extensive site access was needed to measure and scope a renovation that included units, exteriors, amenities and common areas. Next, Catalyst would typically source an interior designer who would site-walk, re-design and specify FF&E for the clubhouse, gym, lobbies and hallways on four floors. A sizable portion of the 500+ man-hours needed pre-construction would require Construction Operations to compile design packages for RFPs, gather and finally level-set multiple contractor bids. Multiple new hires would be required to manage a renovation of this scale. If any takeoffs were discovered to be inaccurate mid-project, costly change orders, rework loops and rebidding would be required to move forward.

“Normally, the timeline from when you close to when you have detailed hard bids is six months or more.”

Dave Denslow, Construction Operations - Catalyst Housing Group

“Normally, the timeline from when you close to when you have detailed hard bids is six months or more.”


Dave Denslow, Construction Operations - Catalyst Housing Group

Benefits

Scalability


“Tailorbird offered us a nine-month improvement over time compared to projects I’ve seen that are similar in scope,” says Dave Denslow, Construction Ops, Catalyst Housing Group

“We couldn’t do what we’re doing without Tailorbird given the number of acquisitions we’re working through. There’s just no way,” highlights Laine Gomez, Asset Management, Catalyst Housing Group

Transparent Transactions

“We’re seeing reduced changed orders to even no change orders because of how well Tailorbird coped out the project ahead of time. It is head and shoulders above anything else out there,” notes Dave Denslow.

“Tailorbird offers us visibility of the construction process in a way where we’re not running into hiccups like costly rework loops and rebidding,” explains Tobi Wray, Owner at Design Well Spent Co.

Results

Four weeks prior to close of acquisition, Catalyst Housing Group received four sets of fully leveled hard bids without requiring a single site walk. The fully-leveled hard bids arrived within two weeks of property address and rent roll submission.

One week after rent roll and property address submission in the Tailorbird portal, Catalyst was provided with dimensionalized floorplans, an RFP and takeoffs without the need for site walks. This trusted data became the single source of truth for the lightning bid and subsequent leveled bidding template used by all bidding contractors.

Concurrently, Design Well Spent Co. partnered with Tailorbird to manage all the conceptual designs and specifications for the complex’s clubhouse, gym, hallways, and lobby renovations.


Benefits

Scalability

“Tailorbird offered us a nine-month improvement over time compared to projects I’ve seen that are similar in scope,” says Dave Denslow, Construction Ops, Catalyst Housing Group

“We couldn’t do what we’re doing without Tailorbird given the number of acquisitions we’re working through. There’s just no way,” highlights Laine Gomez, Asset Management, Catalyst Housing Group

Transparent Transactions

“We’re seeing reduced changed orders to even no change orders because of how well Tailorbird coped out the project ahead of time. It is head and shoulders above anything else out there,” notes Dave Denslow.

“Tailorbird offers us visibility of the construction process in a way where we’re not running into hiccups like costly rework loops and rebidding,” explains Tobi Wray, Owner at Design Well Spent Co.

Results

Four weeks prior to close of acquisition, Catalyst Housing Group received four sets of fully leveled hard bids without requiring a single site walk. The fully-leveled hard bids arrived within two weeks of property address and rent roll submission.

One week after rent roll and property address submission in the Tailorbird portal, Catalyst was provided with dimensionalized floorplans, an RFP and takeoffs without the need for site walks. This trusted data became the single source of truth for the lightning bid and subsequent leveled bidding template used by all bidding contractors.

Concurrently, Design Well Spent Co. partnered with Tailorbird to manage all the conceptual designs and specifications for the complex’s clubhouse, gym, hallways, and lobby renovations.

Before Clubhouse
After Clubhouse
Before Clubhouse
After Clubhouse

“Tailorbird offers line-item budget numbers in a format that’s easy for us to work backwards from so that we’re not specifying things that ownership can’t afford. It keeps us efficiently moving in the right direction.”


Tobi Wray, Owner - Design Well Spent Co.

Results

Within 9 days of property address and rent roll submission, Tailorbird’s solution provided Bascom with a smart RFP containing dimensionally viable floor plans and four fully leveled hard bids without the need for site walks. The cost summary demonstrated the potential of 6.5-8% savings on interior renovations based on the four solicited bids.

“Knowing we can go to Tailorbird with any new acquisition and ask to have interiors bid out to four
reputable groups this quickly is simply an option we’ve never had before at Bascom,” shared Ferrell.

JT Houston, Senior National Account Executive at ReNu Inc was happy to participate in the RFP for the Enclave at Lake Ellenor given his experience using the Tailorbird solution on Greystar, Starwood and Cortland RFP’s. He highlighted, “Tailorbird’s bidding process allowed us to bid more efficiently. We didn’t have to be there. That saves us quite a bit of time because we didn’t have to schedule a trip

and walk all the units.

Typically, this could take us anywhere from four to seven days.” Houston and English described their eagerness to be a part of Tailorbird’s network of contractors. English detailed, “Frequently, the expectation of national contractors with local footprints is that we’ll have a larger price tag because we’re a big machine. It’s simply untrue. Tailorbird offers us the opportunity to challenge the misconception of what it means to be a national company and allow us to rightly be recognized as having a meaningful local presence in the markets we bid in.” Ferrell sensed deep potential in the deployment of the
Tailorbird solution. “Our first project with Tailorbird was enormously beneficial to us, especially because we determined we could produce time and cost savings while we were still in pre-acquisition.” Looking beyond the scope of his first project, Ferrell envisioned what full deployment could mean for Bascom. “Knowing we now have a go-to solution like Tailorbird offers us new comfort and empowers us to be more competitive in every market, on every acquisition.”

Before Lobby
After Lobby

Wray has since partnered with Catalyst Housing Group on multiple multifamily renovations. She continues, “working with Catalyst has been exciting for us [...] we’re looking ahead together and systematizing the scoping and construction process to avoid rework and rebidding. A huge part of that is due to working with Tailorbird.”

In 2021, Catalyst Housing Group was the biggest buyer in the San Francisco metropolitan area, paying a combined $663 million for five assets encompassing 1,226 units. With Tailorbird’s 98.5% accurate measurements and takeoffs, it’s easier for Catalyst to accelerate their velocity of multifamily acquisitions.

Before Lobby
After Lobby

Wray has since partnered with Catalyst Housing Group on multiple multifamily renovations. She continues, “working with Catalyst has been exciting for us [...] we’re looking ahead together and systematizing the scoping and construction process to avoid rework and rebidding. A huge part of that is due to working with Tailorbird.”

In 2021, Catalyst Housing Group was the biggest buyer in the San Francisco metropolitan area, paying a combined $663 million for five assets encompassing 1,226 units. With Tailorbird’s 98.5% accurate measurements and takeoffs, it’s easier for Catalyst to accelerate their velocity of multifamily acquisitions.

“Historically, we couldn’t do what we’re doing right now without involving Tailorbird. you would have to hire extra people to manage this level of acquisitions and renovations. We now allow Tailorbird to be that scalable piece for us.”


Dave Denslow, Construction Operations - Catalyst Housing Group

Tags

READY TO RENOVATE?

/Get Started
with Tailorbird

Contact:
Thank you! Your submission has been received!